Installation
A typical Grit King® Process
can be installed in 3 to 5 days, depending on the scope of
the contract.
Typically the mechanical installation includes for the
off-loading of the individual component items which usually
comprise the following items: Separator, Pump, Classifier,
and interconnecting pipework. These items are positioned
and bolted down on prepared foundations constructed by
others to Hydro International's dimensions. The items are
then connected together with the pipework.
If electrical
installation is required then cable ducts will provided
by the Client and Hydro International will cable between
the items and the Control Panel. |
 |